This website is not affiliated with, sponsored by, or approved by SAP AG.

Convert DP Planned Order to PPDS Planned Order

APO: Advanced Planning and Optimization

Moderators: Snowy, thx4allthefish

Convert DP Planned Order to PPDS Planned Order

Postby Guest » Wed Mar 17, 2004 4:06 am

Hi,
I've cretaed an integration model to transfer Planned Orders from APO to R/3. When I create an SNP Planned Order the data transferred to R/3 is the same as in APO, but when I convert the SNP order to a PPDS order the dates transferred to R/3 is not the same as in APO.
I've checked if there are user-exits in order to solve this, but I only found user-exits in R/3:
- EXIT_SAPLCORD_004
- EXIT_SAPLCORD_005
Using these user exit I was not able to change any date. Does anyone know ho to use these user exits and is there is any other one from APO?

Thanks in advance,

Joan
Guest
 

Re: Convert DP Planned Order to PPDS Planned Order

Postby geoffreyboy » Mon Sep 17, 2012 7:55 pm

Same question.
geoffreyboy
 
Posts: 52
Joined: Mon Oct 09, 2006 11:22 am

Re: Convert DP Planned Order to PPDS Planned Order

Postby apo klaus » Fri Nov 02, 2012 1:00 am

Hi Joan,

if planned orders have diffenrent dates in APO and in R/3
you might check the basic settings

Material master:
float after production
float before production
should both be set to zero

Customizing:
you have to deactivate "scheduling" of planned orders
to see APO dates in R/3

Rgds Klaus
apo klaus
 
Posts: 100
Joined: Fri Apr 09, 2004 2:00 pm
Location: Germany


Return to APO and SCM

Who is online

Users browsing this forum: No registered users and 2 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.