Postby TJ » Tue Oct 22, 2002 5:59 am

Hi,

When i load Data from R/3 to BW as a background job ,with PSA and then into data targets (packet by packet) option,
The process runs as a background process during the R/3 -> PSA stage and then it runs as a Dialog Process during PSA -> Data target Stage .
The ALEREMOTE user is configured as a communication user.
Should the process be runing as a dialog process ? if not where do i fix it ?

the reason is ,i am doing a lot of calculations/updation in the update rules and becos of the process being Dialog,it gets timed out after the set timout. one option to fix this problem is to increase the time out period. is there any other way ?

regards
TJ
Change is The only Constant Factor in Life
TJ
 
Posts: 87
Joined: Tue Oct 22, 2002 5:45 am
Location: UK (Birmingham)

Postby El Belgio » Thu Oct 24, 2002 1:50 am

Have you tried loading into PSA (option 3 without the "Update subsequently in data targets" flag marked) and later on filling your Cube (or ODS) from the PSA?

Cheers,

El Belgio
El Belgio
 
Posts: 2576
Joined: Tue Oct 22, 2002 7:15 am
Location: back in rainland

Postby TJ » Thu Oct 24, 2002 6:08 am

I am using the 3rd option Now.

But i cannot schedule the load from PSA to cube, before the data is loaded into the PSA. i need to schedule this in one shot.

TJ
Change is The only Constant Factor in Life
TJ
 
Posts: 87
Joined: Tue Oct 22, 2002 5:45 am
Location: UK (Birmingham)


Return to Business Warehouse

Who is online

Users browsing this forum: No registered users and 6 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.