RMDATIND for multiple plants in LSMW

Development (ABAP Development WorkBench, ABAP/4 programming)

Moderators: Snowy, thx4allthefish, YuriT, Gothmog

Post Reply
RGoeken
Posts: 45
Joined: Fri Aug 11, 2006 3:18 am

RMDATIND for multiple plants in LSMW

Post by RGoeken » Fri Mar 08, 2013 4:01 am

Hi,

I have the following requirement: We want to do a mass upload of materials for multiple plants and sales organizations with internal numbering.
I am using RMDATIND in LSMW and it is working perfectly but it is only creating every material once for one plant.
Due to the internal numbering I also don't know the material number at the time of migrating.
Does anyone know a good scenario for this situation. Maybe a second run after that to extend them?

Thanks,

Robert