Work Processes are not available for RFCs

Basis (Basis Technology Modules: Basis Component/System Administration, GUIs)

Moderators: Snowy, thx4allthefish

Work Processes are not available for RFCs

Postby AmitChaturvedi16 » Wed May 21, 2014 8:47 am

Dear Experts,

We have a situation in our development system. where the work processes are not available for RFCs.

SARFC screen shot:

System Resources Maximum resources Description
DEV 0 17 Quota for rdisp/rfc_max_queue used up

Parameter:
rdisp/rfc_max_queue = 5
rdisp/rdisp/elem_per_queue= 2000

Server quota for RFCs (SARFC):

Activated (0 or 1)= 1
Max.No.of Requests in Queue= 5
Maximum Number of Logons (%= 90
Maximum No. Separate Logons= 25
Maximum Number of Used WPs= 75
Minimum Number of Free WPs= 1
Maximum No.of Comm. Entries= 90
Maximum Wait Time (Seconds)= 15

Now work process distribution:
DIA=18
BTC=14
UPD=3
UPD2=1
SPO=2
ENQ=1

Maximum work processes are in waiting state. though we are getting 0 resources in SARFC in development system, though the same configuration is perfectly working in production system.

Functional teams are complaining that the processes are not available for RFCs. May I please request your time to suggest a way out?

Thank you So much.

Thanks & Regards
Amit Chaturvedi
AmitChaturvedi16
 
Posts: 4
Joined: Wed May 21, 2014 7:15 am

Re: Work Processes are not available for RFCs

Postby AmitChaturvedi16 » Thu May 22, 2014 11:52 am

Hello Guys,

This issue is fixed, One dialog process was on Hold with RFC. Killing that process released all the resources. But could not understand how one dialog process can hold all the available resources of RFC.

Thanks
Amit
AmitChaturvedi16
 
Posts: 4
Joined: Wed May 21, 2014 7:15 am


Return to Basis

Who is online

Users browsing this forum: No registered users and 2 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.