Postby SAPHER » Tue Feb 26, 2013 11:53 am

Hello,
I'm trying to find a way to enforce time evaluation for days in the future from the PTMW level.
I have set the possibility of evaluation in the future (CHECK FUT function) in the schema and it perfectly works when I put the future date in the "Evaluation up to" field in PT60 transaction.
But system do time evaluation only to current date when I run this from PTMW even if I save future date in the RPTIME00 variant (this one called by LLREP TIME feature).
Do you know how to enforce time evaluation with future date from PTMW?
Will be very grateful for any guideline.

Sapher
--------------------------
SAPHeR
SAPHER
 
Posts: 6
Joined: Wed Nov 05, 2003 9:27 am
Location: Poland

Re: PTMW - time evaluation in the future

Postby SAPHER » Tue Feb 26, 2013 1:31 pm

Small correction - time evaluation from PTMW made calculation with future date when I saved this date in "Evaluation up to" field in the variant. But it is not a good solution because it increase administrator work and is not flexible.
How to transfer the target date from PTMW to RPTIME00???
--------------------------
SAPHeR
SAPHER
 
Posts: 6
Joined: Wed Nov 05, 2003 9:27 am
Location: Poland

Re: PTMW - time evaluation in the future

Postby b123rich » Wed Mar 13, 2013 9:48 am

Hello,
You can change the date of 'evaluation up to' in the saved variant of RPTIME00 used by PTMW.

EXAMPLE
Evaluation up to: D = Current date + 2 days
b123rich
 
Posts: 112
Joined: Thu Mar 23, 2006 4:26 pm

Re: PTMW - time evaluation in the future

Postby SAPHER » Wed Mar 20, 2013 2:15 pm

This is what I wrote above. But it is not a good solution to change the date in the variant each month.
--------------------------
SAPHeR
SAPHER
 
Posts: 6
Joined: Wed Nov 05, 2003 9:27 am
Location: Poland

Re: PTMW - time evaluation in the future

Postby rangachary » Sun Mar 24, 2013 12:27 pm

You don't have to change the variant every month
you can set it to always run upto Current Date + 2 days
rangachary
 
Posts: 921
Joined: Sun Nov 24, 2002 3:44 am
Location: M42 - M5


Return to Human Resources

Who is online

Users browsing this forum: No registered users and 1 guest





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.