ECC 6.05 Equipment Confirmations in CAT2

Human Resources (PM, OM, PA, TM ,PD)

Moderators: Snowy, thx4allthefish, muhnkee_2

Post Reply
mhodgman
Posts: 1
Joined: Tue Apr 10, 2012 10:21 am

ECC 6.05 Equipment Confirmations in CAT2

Post by mhodgman » Tue Apr 10, 2012 10:31 am

Is there anything new in Enhancement Pack 5 that will allow equipment confirmations in CAT2? I can't find anything in the literature, so I thought I would ask the hands-on experts.

didier
Posts: 2409
Joined: Thu Apr 29, 2004 3:33 pm

Re: ECC 6.05 Equipment Confirmations in CAT2

Post by didier » Tue Apr 10, 2012 2:58 pm

hello,

I never heard about an 'equipment confirmation' in PM.

CATS allows to post hours on PM orders, PS networks, CO objects (WBS element, cost centre, internal order) or can create Service entry sheets . Or you can registre HR absesnces, etc.

Didier

Count
Posts: 1373
Joined: Thu Feb 15, 2007 6:28 am

Re: ECC 6.05 Equipment Confirmations in CAT2

Post by Count » Thu Apr 19, 2012 9:27 pm

ok this answer is not related to the question but certainly cats related .... here goes:
1. cats is for times by employees only.
2. nope machine time cannot be done in cats.
3. am not a logistics guy but can give an example of how machine times can be captured:
take pp for example ... and you have a set of production processes which use equipment you can 'plan' your steps in each process.. assign 'activity' to each step,.. (activity is costed by the way)..and based on the actual time booked by a person to do a task can derive the machine hours and the cost of it via the activity... capisce? I warned you I aint a logistics guy :P
cheers
-------------------------------------------