by hrdan » Thu Mar 22, 2012 8:38 am
Hi,
Am having a blonde moment ...
Does a change to the holiday calendar in SAP via SCAL require the associated WSRs to be regenerated ?
Am getting inconsistent results ... in dev box was fine, in QA box when I run PT63 I cannot see the correct holidays being aplied to the persons schedule.
Thanks
-
hrdan
-
- Posts: 53
- Joined: Thu Mar 09, 2006 9:22 am
by rangachary » Thu Mar 22, 2012 10:12 am
Yes, you need to regenerate all the WSRs assigned to the Holiday calendar and transport to all clients.
-
rangachary
-
- Posts: 929
- Joined: Sun Nov 24, 2002 3:44 am
- Location: M42 - M5