Search found 67 matches

by spedge
Tue Feb 13, 2007 8:28 am
Forum: Logistics PS
Topic: Change in "Durat" field after Partial Confirmat &a
Replies: 11
Views: 6703

hi , what you say is something that depends on the settings in the transaction OPU6.There if u check the SHIFT ORDER indicator then the system will not take into account the actual dates while rescheduling the partialy confirmed activities. if this does not meet ur requirements then i will look into...
by spedge
Tue Feb 13, 2007 6:23 am
Forum: Logistics PS
Topic: Change in "Durat" field after Partial Confirmat &a
Replies: 11
Views: 6703

hi, this is standard SAP as u say.here the duration shown is the duration left in the task completion.the normal duration field retains the value you are talking of i.e.the duration required to complete a task in totality. if u need this data in some report then u resort to this field as its a part ...
by spedge
Sat Feb 10, 2007 12:27 am
Forum: Logistics PS
Topic: How to Link Network Activity and PO
Replies: 5
Views: 2766

hi selva,

can u specify what kinds of modifications are required?

thanks and regards
shekhar
by spedge
Wed Feb 07, 2007 2:10 am
Forum: Logistics PS
Topic: Project Creation w/o B.A.
Replies: 5
Views: 901

hi, i have got the solution to the problem. its right that we do not need to give BA while creating a project.but for this the setting is not exactly in the PS configuration.Instead there is a setting to be done in FI..TCode-OBY6(Change Company Code Global Data).there in the Processing Parameters we...
by spedge
Tue Feb 06, 2007 8:09 am
Forum: Logistics PS
Topic: Activity price calculation logic
Replies: 4
Views: 1282

hi, one way to calculate the price of the activity/hr would be to go into the tcode-cnr2...give ur work centre and go to the costing tab.there u can check the value -which the formula defined- calculates for your activity.here check what value comes.the system takes this value as the value of the wo...
by spedge
Tue Feb 06, 2007 5:38 am
Forum: Logistics PS
Topic: Activity price calculation logic
Replies: 4
Views: 1282

hi pssap,

is the activity price of 1.54/hr calculated manually or u have taken the system help to calculate it in the work centre screen?

thanks and regards
shekhar
by spedge
Tue Feb 06, 2007 5:31 am
Forum: Logistics PS
Topic: Project Creation w/o B.A.
Replies: 5
Views: 901

hi pssap,

i did not get u....opsa is the tcode for creating/changing project profile.what about that?can u be a bit more specific?

thanks and regards,
shekhar
by spedge
Tue Feb 06, 2007 2:42 am
Forum: Logistics PS
Topic: Project Creation w/o B.A.
Replies: 5
Views: 901

Project Creation w/o B.A.

hi friends,

can i create a project without giving the Business Area?

thanks and regards
shekhar
by spedge
Mon Feb 05, 2007 8:33 am
Forum: Logistics PS
Topic: Confirmation of an Activity in FS Relatioship
Replies: 1
Views: 719

Confirmation of an Activity in FS Relatioship

hi friends, the scenario is-2 activities in a network with an FS relatioship-1st activity finishes and then the 2nd one starts. if i confirm the 2nd activity by 100%(final confirmation) without confirming the 1st one the system does nt restrain me. can u kindly let me know if any setting is required...
by spedge
Sat Feb 03, 2007 1:04 am
Forum: Logistics PS
Topic: Confirmations in Project Builder
Replies: 3
Views: 647

hi kadootty,

thanks a lot...i get your point.but one thing..this percentage thing the system determines itself or we have to give any arbitrary %age.


thanks and regards,
shekhar.
by spedge
Fri Feb 02, 2007 8:45 am
Forum: Logistics PS
Topic: Confirmations in Project Builder
Replies: 3
Views: 647

Confirmations in Project Builder

hi, i have to confirm an activity through the project builder. The activity has started but has not completed as yet.the system does not allow me to put only the actual start date-the actual finish date has also to be put in.my question is that why do we need to give the actual finish date when my w...
by spedge
Wed Jan 17, 2007 2:31 am
Forum: Logistics PS
Topic: PR not reflected as committment items in the report
Replies: 3
Views: 798

dear ananth, cost elements are assigned to the particular committment...i think thats the reason why the earlier PRs are being reflected as the commitments. one thing i noticed is that in the repport S_ALR_87013542...alongwith the comittments the created PRs values are not getting reflected for the ...
by spedge
Mon Jan 15, 2007 5:53 am
Forum: Logistics PS
Topic: PR not reflected as committment items in the report
Replies: 3
Views: 798

PR not reflected as committment items in the report

dear friends, i have recently activated project cash managment and committment management in cstomization.now the problem is that the earlier created PRs are being reflected as coomittments in the reports while the ndew PRs are not... what cud be the possible reason? thanks and regards, shekhar
by spedge
Thu Jan 04, 2007 2:58 am
Forum: Logistics PS
Topic: Monitoring of Proj Progress in the subcontracted Activities
Replies: 6
Views: 1490

thanks AK.

my concern is that should the activities be managed as internal activities or otherwise?as all the works are outsourced..conceptually no work centres..but can the monitoring be done at the external activity level?

thanks
by spedge
Mon Jan 01, 2007 5:12 am
Forum: Logistics PS
Topic: Monitoring of Proj Progress in the subcontracted Activities
Replies: 6
Views: 1490

Monitoring of Proj Progress in the subcontracted Activities

We are implementing PS for a real estate company. The company is in the business of Constructing residential and commercial complex. All the company activities are subcontracted. The client wishes to monitor all the subcontracetd activites.On the basis of the work development, payments are made to t...