Search found 87 matches

by shareeq
Sun Nov 30, 2014 5:50 am
Forum: Logistics PS
Topic: if a P.O. was not paid, does it still appears as an actual o
Replies: 1
Views: 3457

Re: if a P.O. was not paid, does it still appears as an actual o

Hi Guest ,

It will appear as Commitment in Project Reports and Not as Actuals.

Thank You,

Shareeq
by shareeq
Sun Nov 30, 2014 5:21 am
Forum: Logistics PS
Topic: How to add material im Activity?
Replies: 1
Views: 3519

Re: How to add material im Activity?

Hi,

Kindly do a crash course .

Thanks,
Shareeq
by shareeq
Sun Nov 30, 2014 5:19 am
Forum: Logistics PS
Topic: WBS with and With out Cost
Replies: 1
Views: 2783

Re: WBS with and With out Cost

Use the Field Project Type.

Thanks,
Shareeq
by shareeq
Sun Nov 30, 2014 5:17 am
Forum: Logistics PS
Topic: Issue of plant stock to a non-valuated project
Replies: 2
Views: 3778

Re: Issue of plant stock to a non-valuated project

If your Plant Stock has value , Accounting document will be created .

Regards,
Shareeq
by shareeq
Sun Nov 30, 2014 5:08 am
Forum: Logistics PS
Topic: How to block Budget w/o P.O. or P.Req
Replies: 1
Views: 2954

Re: How to block Budget w/o P.O. or P.Req

Hello SAPPSMM,

There are 2 options.

1) Create an Service PR Activity under the WBS with the required Value
2) Create an Internal Activity and in the Progress data tab --> general Assignments --> Mat.Planning

Hope it helps.

Regards,
Shareeq
by shareeq
Wed Aug 21, 2013 7:21 am
Forum: Logistics PS
Topic: Activity elements posting hours
Replies: 2
Views: 2932

Re: Activity elements posting hours

Dear Sarajane,

Kindly try out and post here if you face any errors.

Regards,
Shareeq
by shareeq
Mon Aug 19, 2013 7:09 am
Forum: Logistics PS
Topic: VF44 or Project RA
Replies: 2
Views: 2797

Re: VF44 or Project RA

Hi, VF44 is Revenue Recognition, it will not pick Costs. To use VF44 , there are many notes to be appled and you have to get access key from SAP. Activating VF44 is a long process. Kindly get to know the process from your Customer . In my experience , Revenue Recognition means Result Analysis. the U...
by shareeq
Wed Mar 28, 2012 6:06 am
Forum: Logistics PM
Topic: Could not create DMR in DP90
Replies: 2
Views: 588

Re: Could not create DMR in DP90

Dear PJA,

Great. Yup there are -ve costs in the order. thanks to the user who cancelled the goods movement through mb1a and not through MBST.

Thank you very much.

Regards,
Shareeq
by shareeq
Wed Mar 28, 2012 1:28 am
Forum: Logistics PM
Topic: Could not create DMR in DP90
Replies: 2
Views: 588

Could not create DMR in DP90

Dear Experts,

We could not create DMR in DP90. It shows Order type 'CR' has not been defined in Sales area. Message no. V1502

We have created several DMR's in the past. DIP settings are OK. Cost is shown in iw32 --> Costs Tab.

Please help me.

Regards,
Shareeq
by shareeq
Sun Oct 02, 2011 2:32 am
Forum: Logistics PM
Topic: Pop Up On Order Creation
Replies: 1
Views: 588

Pop Up On Order Creation

Dear Experts,

When more than one Order is created for the same Equipment, We Used to get a Pop Up. Now Pop ups are not appearing.

Please help to Locate the Issue.

Regards,
Shareeq
by shareeq
Tue May 17, 2011 11:23 pm
Forum: Logistics PM
Topic: Resuls Analysis for Service Contracts -KKA3
Replies: 1
Views: 1154

Re: Resuls Analysis for Service Contracts -KKA3

Problem solved with User-Exits
by shareeq
Thu Nov 04, 2010 6:54 am
Forum: Logistics PM
Topic: Resuls Analysis for Service Contracts -KKA3
Replies: 1
Views: 1154

Resuls Analysis for Service Contracts -KKA3

Dear Experts, We are running RA for Service Contracts. Contract period is 01/11/2010 to 30/10/2011. Montlhy Value is 1000, Total value of the Contract is 12000. THe Billing Plan is Quarterly in Advance. We have incurred some costs in the month of November 2010. If we RUN RA on KKA3 for the month of ...
by shareeq
Mon Apr 12, 2010 8:02 am
Forum: Logistics PM
Topic: Billing Plan in Service Contracts with multiple prices
Replies: 5
Views: 1577

Re: Billing Plan in Service Contracts with multiple prices

Dear Tim,

We do have the Same Problem. If you have found a solution please let us know.

Regards,
Shareeq

Dear Moderator,
Am not hijacking this post, we just wanted to know if Tim has found a solution.

Regards,
Shareeq
by shareeq
Tue Mar 09, 2010 11:35 pm
Forum: Logistics PS
Topic: Project updation
Replies: 2
Views: 1985

Re: Project updation

Note 896429 solves the problem of Copying Projects User status to all WBS Elements User Status.
Regards,
Shareeq
by shareeq
Mon Mar 08, 2010 11:16 pm
Forum: Logistics PS
Topic: Project updation
Replies: 2
Views: 1985

Re: Project updation

Dear prosys,

if you have found a solution please update the post. We are facing the same problem.

The User Status is not copied to the WBS Elements from the Project.

Regards,
Shareeq